Page 1 of 1

Automatic Update of reports

PostPosted: Wed Oct 05, 2011 4:13 pm
by Jacques
Hi,
Is it possible to automatically update a report with graphs each x minutes ?
The target is to have a big screen in a room with a graph showing the evolution of an event during the day. It could be percentage of work having been done, evolution of the number of parts produced, ...

Jacques

Re: Automatic Update of reports

PostPosted: Wed Oct 05, 2011 5:01 pm
by admin
Hi Jacques,

Yes we can!
Put the chart on a dashboard, then go in design mode on the dashboard. Here you'll find optional.to.reload.every x seconds. Don't set it too low.

Enjoy :)
Bo

Re: Automatic Update of reports

PostPosted: Wed Oct 05, 2011 7:33 pm
by Jacques
Thanks Bo

I have found that the report to put in the package must be a "graph only".
With other typ of report, the column "Refresh in second" doesn't exist !
It was the reason I didn't found it.

Jacques